How long does a bathroom renovation take?

By Redone Right · 24 November 2026

Most bathroom renovations take between 2 and 15 working days on site, depending on the room. A cloakroom WC is usually done within a week, while a family bathroom or wet room takes two to three weeks. Planning and ordering happen before that, and with a design and build company they run side by side, so the clock on site starts only when everything is ready.

These are the same typical timescales as in our bathroom cost guide.

RoomTypical time on site
Cloakroom or downstairs WC2 to 5 working days
Bath swapped for a walk-in shower3 to 5 working days
En-suite or shower room5 to 10 working days
Family bathroom7 to 15 working days
Wet room7 to 15 working days
Large or re-planned bathroom9 to 16 working days

These are typical UK timescales, not promises. A fixed quote from Redone Right gives your own start and finish dates.

Before the work starts: design and ordering

The time before anyone picks up a tool matters as much as the build. At Redone Right this is where the design happens:

  1. Design consultation. We measure, check the pipework and drainage, and talk through layout, storage and light.
  2. Design and selections. You choose tiles, fittings and finishes with our help, so everything works together.
  3. Fixed quote and dates. An itemised quote with a start date.
  4. Ordering. Everything is ordered and delivered before day one, so the job never stops to wait for a part.

Most delays on bathroom jobs happen because something wasn’t decided or wasn’t delivered. Designing first and ordering early is the simplest way to keep the build short.

Strip-outReal job · back to the walls

What happens day by day (a typical family bathroom)

  1. Days 1 to 2: strip-out. Old suite, tiles and boards come out; floors are protected and waste removed.
  2. Days 2 to 4: first fix. New pipework, waste and wiring are run while the walls are open. Electrical work is done by a Part P registered electrician.
  3. Days 4 to 6: boards and waterproofing. Walls are boarded, shower areas waterproofed.
  4. Days 6 to 10: tiling. Usually the longest single stage. Large-format and natural stone tiles take longer.
  5. Days 10 to 13: second fix. Toilet, basin, bath or shower, furniture, lighting and extractor fan are fitted.
  6. Last day: finish. Sealing, cleaning, testing and a walk-through with you.

What makes a bathroom take longer?

Can I use the bathroom during the work?

Not usually, once the strip-out has started. If it’s your only bathroom, ask about keeping a working toilet for as much of the job as possible. With an en-suite or cloakroom you normally still have the main bathroom, so disruption is low.

Frequently asked questions

How long does it take to fit a new bathroom suite only?

Swapping a suite like for like, without re-tiling, is much quicker than a full renovation. The time depends on how much else needs changing, which we check at the design consultation.

How long does tiling a bathroom take?

Usually several days, and it is often the longest single stage. Walls and floors in a family bathroom typically take 3 to 5 days.

Why does a small bathroom take nearly as long as a big one?

The same stages happen in the same order: strip-out, plumbing, boarding, tiling, fitting. A small room saves on tiling time, but not much else.